July 06, 2010
|
 |
|
|
|
Within the following-up on implementation of the underground lines, Prime Minister Dr. Ahmed Nazif held a meeting in attendance of the Minister of Transport and Chairman of the Underground Authority.
The Minister of Transport reviewed a report on development of various underground lines implementation particularly the third line. It was mentioned that the first phase of the third line would be completed by October 2011 and the second phase would be completed by October 2013.
Regarding the underground's fourth line, the Transport Minister noted that the feasibility study was completed during the last month in cooperation with Japan International Cooperation Agency (JICA). He clarified that detailed studies on the project are currently carried out to be finished by 2011, then to be offered in international bids by the coming year.
It is worth noting that the prime minister will pay a tour visit to the first phase of the third line (Attaba-Abasyia) to inspect work therein, where 90% of main actions were finished.
|
|
|
|
|
|
|
|